Modernisation of MMIA Terminal 1 has moved from plans to visible delivery – Kuku

23

The Managing Director/CE, Federal Airports Authority of Nigeria (FAAN), Mrs. Olubunmi Kuku, has stated that the rehabilitation and modernisation of Terminal 1 at the Murtala Muhammed International Airport (MMIA), Lagos, is increasingly becoming tangible for Nigerians and international travellers.

On Tuesday, October 6, 2026, FAAN, in collaboration with the China Civil Engineering Construction Corporation (CCECC) and project consultant, ARUP, marked the final concrete pouring for the inbound and outbound landside bridge into the terminal, effectively connecting the entire bridge structure from its starting point to its endpoint.

Mrs. Olubunmi Kuku stated this at the occasion, describing the milestone as another important step in moving the project “from plans to visible delivery.”

She expressed appreciation to His Excellency, President Bola Ahmed Tinubu, GCFR, and the Honourable Minister of Aviation and Aerospace Development, Mr Festus Keyamo, SAN, for their leadership, support and commitment to the successful delivery of the project.

The FAAN boss also acknowledged the efforts of CCECC, ARUP, FAAN’s technical teams and other stakeholders whose collective work continues to drive the project forward.

The event was deliberately kept as a modest media engagement to showcase the progress and traction being achieved on the project to the public, stakeholders, skeptics and the world at large, while providing visible evidence of the Federal Government’s ongoing investment in the transformation of Nigeria’s premier international gateway.

FAAN, however, clarified that today’s milestone does not signify the immediate opening of the bridges for use. The occasion marks the completion of the concrete works. The newly poured concrete will undergo the necessary curing period, after which lighting and other finishing works will be completed in the coming weeks.

The landside bridges are expected to become operational in December 2026, in line with the anticipated completion of the façade and other exterior works of Terminal 1.

The rehabilitation and modernisation of Terminal 1 is part of the Federal Government’s broader effort to upgrade airport infrastructure, enhance passenger experience and position Nigeria’s airports to meet the demands of a modern and increasingly connected aviation environment.